We have been working on a classroom project at Westerings Academy, Southend-on-sea.  This is an eco-timber teaching facility for year 6 pupils.

Build process from start to finish was 3 weeks.

2 week lead time from design and manufacture

The new timber frame was manufactured by Honeybourne offsite to minimise disruption and to accelerate the programme for delivery to our clients.

For further details on the eco-timber frame please contact us